Authorization to create a housing group

Machine-translated — the French version prevails.

An administrative decision that allows a housing group to be built, either all at once or in phases, on one or more plots. It is issued by the president of the communal council (conseil communal), or by the governor if the project covers several communes.

🏛️ Administration
Local authorities (Collectivités territoriales): the Commune (Commune); or the prefecture or province (préfecture ou province) for places of worship or projects spanning several communes
💰 CostTax on subdivision operations: between 3% and 5% of the total cost of development works, excluding VAT (rate set by the commune's tax order). Tax on construction operations: 10 to 20 DH per m² of covered area for apartment buildings, real estate complexes and industrial, commercial, professional or administrative buildings; 20 to 30 DH per m² of covered area for individual homes. Projections over the communal public domain are counted double. Fees for the services of the urban agency (agence urbaine) are set by its own decision.
⏱️ Processing timeAverage time of 60 days (30 days indicated in the official time limits)

📎 Required documents

  • Application signed by the applicant, the design engineer or an authorized representative (template in Annex No. 5 of Decree No. 2.18.577)
  • Identification form signed by the applicant
  • Certificate from the National Agency for Land Registry (Agence nationale de la conservation foncière) confirming that the land is registered or in the registration process
  • Plan from the National Agency for Land Registry showing the boundaries of the land
  • Location plan of the plot at a scale of 1/2000 or 1/5000
  • Topographic plan at a scale of 1/500 or 1/1000
  • Architectural design plan of the housing group at a scale of 1/500 or 1/1000
  • Construction plan of all levels at a scale of at least 1/100
  • Infrastructure design plans at a scale of 1/500 or 1/1000
  • Technical documents on roads and on the water, sewerage and electricity networks
  • Typical cross-sections of the roads
  • Longitudinal profiles of roadways, drainage and water pipes
  • Technical structural, stability and strength plans prepared by specialized engineers
  • Plans of structures at a scale of at least 1/50, where applicable
  • Specifications document (cahier des charges) setting out the easements (servitudes) affecting the land
  • Document setting out the architectural requirements for squares, small squares and roads subject to an architectural harmony easement
  • Technical note on compliance with fire and panic risk prevention rules
  • Technical note from the architect on compliance with energy efficiency rules
  • Copy of the contracts signed with the engineers involved in the project
  • Site logbook (cahier de chantier) in line with the administration's template
  • Copy of the payment receipt for paid services
  • Previously authorized plan of the housing group (in case of modification, renewal or new construction within an already authorized group)

✅ Conditions and how to apply

  • The land must be registered or in the process of being registered, with no objection once the objection period has expired
  • The application must be filed at the prefecture or province if the project is for a place of worship or covers two or more communes

⚖️ Legal references

Law No. 25.90 on subdivisions, housing groups and land division (Dahir No. 1.92.7 of 17 June 1992); Law No. 12.90 on urban planning (Dahir No. 1.92.31); Decree No. 2.92.833 of 12 October 1993; Decree No. 2.22.141 of 8 May 2023; Joint Order No. 1839.23 of 10 July 2023 setting the time limits

Other procedures : Housing, real estate and transport

All procedures: Housing, real estate and transport →

Official source : Idarati.ma — checked on November 5, 2026