Medium-voltage (HTA) electricity grid connection works
Procedure for having a project connected to the medium-voltage electricity grid, carried out either by the distributor or by an authorized outside contractor. A final invoice is issued at the end of the works, based on the quantities actually carried out.
📎 Required documents
- Commitment to pay the amount of the quotation and the final invoice, with payment of the first instalment
- Rights of way and land crossing permissions (motorway, communes, Ministry of Equipment, etc.)
- Copy of the building permit for the electrical transformer
- If the works are entrusted to an outside contractor: application for authorization to carry out the works, submitted by the developer, with the technical and administrative references of the chosen contractor
- If the works are entrusted to an outside contractor: copy of the special technical specifications (cahier des prescriptions techniques particulières), signed and initialed on each page
- If the works are entrusted to an outside contractor: declaration of commitment to comply with the general and special technical specifications and with the standards in force
- If the works are entrusted to the distributor: works contract signed between the customer and the distributor (execution deadlines and payment terms)
⚖️ Legal references
Decision No. 67-350 of 15 July 1967 of the Minister of Public Works and Communications; Joint Order No. 337.20 of 21 January 2020; Joint Order No. 338.20 of 21 January 2020; Order of the Minister of the Interior No. 1025.23 of 3 July 2023 (implementing Article 5 of Decree No. 2.22.141 issued for Law No. 55.19); decisions of the boards of directors of the agencies (régies); delegated management contracts; distributor's specifications (cahiers des charges)
Other procedures : Housing, real estate and transport
- Subdivision Permit (Autorisation de lotir)
- Authorization to subdivide a real estate property
- Obtain a Quote for Supplying Water, Sanitation and Electricity to a Subdivision or Housing Group
- Authorization to create a housing group
- Connecting a Subdivision or Housing Group to the Drinking Water, Sewerage and Electricity Networks
- Carrying out individual connection works for drinking water, wastewater sanitation and low-voltage electricity
- Get the price list for social connection to water, sanitation and electricity
- Social connection to the drinking water, wastewater sanitation and electricity networks
Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.