Get a quote for an individual connection to water, sewerage and low-voltage electricity

Machine-translated — the French version prevails.

This procedure lets you get a quote from your local utility provider for connecting a building to the drinking water, wastewater sewerage and low-voltage electricity networks. The amount depends on the provider, the distance and the work required.

🏛️ Administration
Autonomous distribution agencies and delegated management companies (Régies autonomes de distribution et sociétés de gestion déléguée) such as Lydec, Redal, Amendis, RADEEMA, RADEEF, etc.
💰 CostAmounts vary depending on the utility provider, the connection distance and the equipment work required. They include: contributions to infrastructure; contribution to increasing electrical power or reinforcing water flow; connection/service line/inspection costs and road resurfacing tax where applicable; network extension costs where applicable; fees and work monitoring costs; VAT. For customers without a standard quote or with a flat-rate fee, a final invoice is issued after the work is done and may lead to an additional charge or a refund. Rates can be viewed on each utility provider's portal.
⏱️ Processing timeAverage time of 14 days; price statement for the connection: 10 days.

📎 Required documents

  • Completed connection request form (available from the utility provider or downloadable via its digital agency)
  • Copy of the National ID card (CIN), residence permit or passport (CIN of the manager for legal entities)
  • Copy of the commercial register (Registre du commerce) extract (for companies)
  • Copy of the Common Company Identifier (ICE) certificate (for companies)
  • Copy of the articles of association (statuts) (for legal entities)
  • Copy of the property deed (land title, notary's certificate, certificate of ownership or any document proving ownership)
  • Copy of the approved building plans: layout plan, site plan and façade plans
  • Architect's certificate stating the table of built areas, the number of floors and the composition of the building
  • Copy of the building permit
  • Exceptional authorization from the competent authority if there is no building permit and no plans
  • Undertaking to pay the contribution to the sewerage network for areas not yet served
  • Form stating electricity needs (kVA) and/or drinking water needs (m3/day), if the utility provider requests it

⚖️ Legal references

Dahir No. 1-92-31 of 15 Hijja 1412 (17 June 1992) promulgating Law No. 12-90 on urban planning; Decree No. 02-18-577 of 8 Chaoual 1440 (June 2019) approving the general construction code; Decision No. 67-350 of 15 July 1967 of the Minister of Public Works and Communications; Joint Order No. 337.20 of 25 Joumada Al Awwal 1441 (21 January 2020); Joint Decision No. 338.20 of 25 Joumada Al Awwal 1441 (21 January 2020); Order of the Minister of the Interior No. 1025.23 of 14 Hijja 1444 (3 July 2023)

Other procedures : Housing, real estate and transport

All procedures: Housing, real estate and transport →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.