Obtaining a quote for connection to the medium-voltage (HTA) electricity grid
Machine-translated — the French version prevails.
Procedure for receiving from the electricity distributor a quote with the cost of connecting a project to the medium-voltage grid. The amount depends on the distributor, the connection distance and the work required.
🏛️ Administration
Water and electricity distribution agencies and companiesRADEEMA, RADEEF, RADEM, RAK, RADEEJ, RADEES, RADEEL, Lydec, Redal, Amendis
💰 CostAmounts vary depending on the distributor, the connection distance and the equipment work (contributions to infrastructure, possible contribution for a power increase, MV/LV transformer substation, MV connection and extension, follow-up fees, VAT). A final invoice is issued after the work, based on the quantities actually carried out. Details are available on the distributor's portal (e.g. www.lydec.ma, www.redal.ma, www.amendis.ma, www.radeef.ma).
⏱️ Processing timeAverage time of 45 days; price statement for the HTA connection: 28 days.
📎 Required documents
- Connection request with the contractor's contact details (address, phone, fax, e-mail)
- Statement of the electrical power needed
- Copy of the National ID card (CIN) of the manager or contractor
- Copy of the commercial register (Registre de commerce) (for companies)
- Copy of the Common Company Identifier certificate (Identifiant Commun de l'Entreprise, ICE) (for companies)
- Copy of the articles of association (statuts) (for legal entities)
- Owner: copy of the proof of ownership (land title, notary certificate, deed of ownership, or certificate of ownership or right of disposal issued by the competent authority)
- Tenant: the owner's authorization and a copy of the lease contract
- Copy of the approved project location plan, showing access roads (electronic and paper formats)
- Copy of the approved site plan or architectural plan at 1/500 scale, approved by the Commune (Commune), bearing the mentions "NE VARIETURE" and "Avis favorable" (electronic and paper formats)
- Copy of the building permit approved by the competent authorities
⚖️ Legal references
Decision No. 67-350 of 15 July 1967 of the Minister of Public Works and Communications; Joint Order No. 337.20 of 21 January 2020; Joint Order No. 338.20 of 21 January 2020; Order of the Minister of the Interior No. 1025.23 of 3 July 2023; decisions of the boards of directors of the agencies (régies); delegated management contracts; distributor's specifications (cahiers des charges)
Other procedures : Housing, real estate and transport
- Connecting a Subdivision or Housing Group to the Drinking Water, Sewerage and Electricity Networks
- Carrying out individual connection works for drinking water, wastewater sanitation and low-voltage electricity
- Get the price list for social connection to water, sanitation and electricity
- Social connection to the drinking water, wastewater sanitation and electricity networks
- Building Repair Permit
- Connecting a standalone building to the drinking water, sanitation and low-voltage electricity networks
- Cancel your drinking water and/or electricity subscription
- Medium-voltage electricity subscription with the distributor
Official source : Idarati.ma — checked on November 5, 2026