Provisional authorization to build a renewable energy electricity production facility
This procedure allows you to obtain the provisional authorization required before building a facility that produces electricity from renewable sources. It is issued if the conditions set by the legal texts are met.
📎 Required documents
- Names of the chairperson and members of the board of directors or supervisory board (public limited companies)
- Names of the managers and members of the supervisory board (partnerships limited by shares and limited liability companies (SARL))
- Names of all partners (general partnerships and limited liability companies (SARL) without a supervisory board)
- Names of the managers authorized to bind the company with their signature
- Statement that the company is being formed, with the known information about the future definitive owner (where applicable)
- Name and address of the applicant's agent or representative in Morocco
- For an individual: profession, nationality, place of residence and, if necessary, agent or representative in Morocco
- Precise coordinates of the facility on a 1:50,000 topographic map or another suitable scale, with north-south and east-west boundaries (Lambert or geographic system)
- Renewable energy source, power, production capacity, operating mode and estimated annual and monthly operating times
- Safety and reliability conditions of the works connecting to the national transmission grid and of the equipment, with the required technical characteristics
- General program and schedule of the works to build or extend the facility
- Environmental impact report with key issues, mitigation or compensation measures and a forecast assessment of greenhouse gas emissions
⚖️ Legal references
Renewable Energy Law; Law No. 58-15 amending and supplementing Law No. 13-09 on renewable energy; Law regulating the electricity sector and establishing the National Electricity Regulatory Authority; Decree on access to the national medium-voltage electricity grid; Decree No. 2-10-578 of 7 Joumada I 1432 (11 April 2011) on renewable energy; Order No. 2657.11 of 20 Chaoual 1432 (19 September 2011) setting the host zones for project development sites for electricity production from renewable energy sources
Other procedures : Energy, minerals and environment
- Renewal of the Authorization to Exploit Mining Waste and Spoil Heaps
- Assessment of Works to Relocate Power Lines
- Authorization for the transit of waste through Moroccan ports
- Obtain a decree cancelling a hydrocarbon exploitation concession
- Authorization to operate a storage depot for liquid petroleum products
- Extension of the provisional authorization to build a renewable energy electricity production facility
- Renewal of a Mining Exploration Permit Resulting from a Merger
- Declare the creation of a storage facility for explosives and blasting accessories for civilian use
Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.