Extension of the provisional authorization to build a renewable energy electricity production facility

Machine-translated — the French version prevails.

This procedure allows you to extend the period of the provisional authorization granted to build a facility that produces electricity from renewable sources, provided the legal conditions are met. It is free of charge and takes 30 days on average.

🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableEnergy Transition Department (Département de la Transition Energétique) (Directorate of Renewable Energies and Energy EfficiencyDirection des énergies renouvelables et de l'efficacité énergétique)
💰 CostFree
⏱️ Processing time30 days

📎 Required documents

  • Reasoned request explaining the progress of the project and the reasons for the delay in its completion

✅ Conditions and how to apply

  • Meet the conditions set out in the legal references

⚖️ Legal references

Dahir No. 1-10-16 of 26 Safar 1431 (11 February 2010) promulgating Law No. 13-09 on renewable energies; Dahir No. 1-16-3 of 1 Rabii II 1437 (12 January 2016) promulgating Law No. 58-15; Dahir No. 1-16-60 of 17 Chaabane 1437 (24 May 2016) promulgating Law No. 48-15 on the regulation of the electricity sector and the creation of the National Electricity Regulatory Authority (ANRE); Decree No. 2-15-772 of 14 Moharram 1437 (28 October 2015) on access to the national medium-voltage electricity grid; Order No. 2657-11 of 20 Chaoual 1432 (19 September 2011)

Other procedures : Energy, minerals and environment

All procedures: Energy, minerals and environment →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.