Obtaining the final authorization to operate a renewable energy electricity production facility

Machine-translated — the French version prevails.

This procedure allows you to obtain the final authorization to operate a facility that produces electricity from renewable sources. It is granted if the conditions set by the legal texts are met and respected.

🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableEnergy Transition Department (Département de la Transition Energétique)Directorate of Renewable Energy and Energy Efficiency / Direction des énergies renouvelables et de l'efficacité énergétique
💰 CostFree
⏱️ Processing time30 days

📎 Required documents

  • Description of the legal structure of the entity that owns the project and operates the facility
  • Description of the operator's technical capacities
  • Description of the operator's experience and summary of its previous achievements, if applicable
  • List of the main roles and duties of the staff, with documents proving their skills
  • List of customers supplied by the facility, with their location and consumption levels (consistent with the authorization)
  • Parcel plan and detailed plan of the facility (access roads, power lines, delivery and connection substations, civil and electrical engineering works)
  • Description of the technical characteristics of the equipment and machines used for production
  • Technical characteristics of the machines the facilities must be equipped with
  • Detailed description of how the facility operates
  • How the technical specifications and standards of the national electricity grid operator will be applied
  • Preventive and corrective maintenance arrangements
  • Description of the means and procedures for optimal operation of the facility
  • Procedure for protecting the facility if technical activities stop
  • Procedure in case of prolonged stoppage of technical activities
  • Any technical constraints (protecting water from pollution, leaks of polluting substances)
  • Procedures and means for connection to the national electricity grid
  • Urban planning measures to be complied with, according to the urban development authorizations granted
  • Safety measures adopted
  • Plans for connection to the national electricity grid, the grouping and evacuation substation, and the water, sanitation (if any) and telecommunications networks
  • Environmental and health impact study, with the environmental approval decision
  • Copies of insurance policies (general liability and professional liability)
  • National Social Security Fund (CNSS) affiliation number and salary declaration
  • Amount of the investment made
  • Complete annual accounts for the last accounting year
  • Financial structure of the project: equity, debt, subsidies and financial incentives

⚖️ Legal references

Dahir No. 1.10.16 of 26 Safar 1431 (11 February 2010) promulgating Law No. 13.09 on renewable energies; Dahir No. 1.16.3 of 1 Rabii II 1437 (12 January 2016) promulgating Law No. 58.15; Dahir No. 1.16.60 of 17 Chaabane 1437 (24 May 2016) promulgating Law No. 48.15 on the regulation of the electricity sector and the creation of the National Electricity Regulatory Authority (ANRE); Decree on access to the national medium-voltage electricity grid; Decree No. 2.10.578 of 7 Joumada I 1432 (11 April 2011); Order No. 2657.11 of 20 Chaoual 1432 (19 September 2011); Order No. 313.14 of 4 Rabii II 1435 (4 February 2014)

Other procedures : Energy, minerals and environment

All procedures: Energy, minerals and environment →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.