Connecting a standalone building to the drinking water, sanitation and low-voltage electricity networks

Machine-translated — the French version prevails.

Procedure for having individual connections made to drinking water, wastewater sanitation and low-voltage electricity for a standalone building. The work can be given to an outside contractor or to the utility provider.

🏛️ Administration
Autonomous distribution utilities (Régies autonomes de distribution) and delegated management companiesLydec, Redal, Amendis, etc.
💰 CostFinal invoice for the infrastructure work (on-site and off-site), issued when the work is completed, based on the work statement (attachement) and the quantities actually carried out, and signed jointly by both parties. The amount varies.
⏱️ Processing time21 days to complete the individual connections for a standalone building

📎 Required documents

  • Commitment to pay the amount of the quote and the final invoice, with payment of the first instalment
  • Rights of way and rights to cross land (motorway, communes, public facilities, etc.)
  • Copy of the building permit for the electrical transformer
  • If the work is given to an outside contractor: request for authorization to carry out the work, with the contractor's technical and administrative references
  • If the work is given to an outside contractor: 2 copies of the special and technical specifications document (cahier des prescriptions particulières et techniques), signed and initialed
  • If the work is given to an outside contractor: 2 declarations of commitment to comply with the general and special technical specifications and the standards in force
  • If the work is given to the utility provider: work contract signed between the customer and the utility provider (completion deadlines and payment terms)

⚖️ Legal references

Dahir No. 1.92.7 of 17 June 1992 (Law 25.90); Dahir No. 1.92.31 of 17 June 1992 (Law 12.90); Decree No. 02-18-577 (General Construction Code); Decision No. 67-350 of 15 July 1967; Joint Order No. 337.20; Joint Order No. 338.20; Order of the Minister of the Interior No. 1025-23 of 3 July 2023

Other procedures : Housing, real estate and transport

All procedures: Housing, real estate and transport →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.