Renewal of a Mining Exploration Authorization
Machine-translated — the French version prevails.
Procedure to extend a mining exploration authorization when exploration work has not been completed. The application is submitted to the Directorate of Mines and Hydrocarbons (Direction des mines et des hydrocarbures).
🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableDirectorate of Mines and HydrocarbonsDirection des mines et des hydrocarbures
💰 Cost100 dirhams/km²
⏱️ Processing time60 days
📎 Required documents
- Number of the exploration authorization to be renewed
- Name, legal form and registered office of the legal entity and, if applicable, the first name, last name, profession, nationality and home address of its representative
- Report on the studies and work carried out, their results and their interpretation, with supporting documents for the expenses incurred
- Work plan at a scale of 1/10000 and an overlay-compatible surface plan
- Program of work planned during the renewal period, with the implementation schedule
- Original receipt of payment of the service fee (100 DH/km²)
✅ Conditions and how to apply
- Mining exploration work must be completed or in progress, depending on the renewal application (source description: completion of mining exploration work)
⚖️ Legal references
Dahir No. 1.15.76 of 14 Ramadan 1436 (1 July 2015) promulgating Law No. 33.13 on mines; Decree No. 2.19.543 of 2 Chaabane 1441 (27 March 2020) amending and supplementing Decree No. 2.15.807 of 12 Rajab 1437 (20 April 2016); Joint Decree No. 2221.20 of 23 Dhul Hijjah 1441 (13 August 2020) revising the service fee provided for in Article 24 of Decree No. 2.15.807
Other procedures : Energy, minerals and environment
- Authorization to operate a depot for civil-use explosives and firing accessories
- Authorization to Relocate a Service Station or a Filling Station
- Renewal of the authorization to use explosives and blasting accessories (immediate use on site)
- Certificate of absence of radioactive contamination (environmental samples, food, water)
- Obtaining authorization to transfer or lease a mining title
- Authorization to Set Up a Bulk Liquefied Petroleum Gas Storage Depot
- Obtain a certificate of insurance or financial security for wreck removal
- Obtaining Approval in Principle for a Piped Propane Distribution Installation