Authorization to Relocate a Service Station or a Filling Station
Machine-translated — the French version prevails.
This procedure allows you to obtain authorization to move a service station or a filling station to a new location. The application is submitted to the Directorate of Hydrocarbons (Direction des hydrocarbures).
🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableDepartment of Energy Transition (Département de la Transition Energétique)Directorate of Hydrocarbons / Direction des hydrocarbures
💰 CostFree
⏱️ Processing time60 days
📎 Required documents
- Application for authorization addressed to the government authority in charge of energy
- Official map at a scale of 1/50,000 or 1/100,000 (or reconnaissance map at a scale of 1/100,000) showing the location of the station and the existing stations within a 50 km radius (rural project)
- Location plan at a scale of 1/2000 if the station is close to a built-up area (rural project)
- Location plan at a scale of 1/1000 showing the streets and existing stations (urban project)
- Descriptive plan of the installations, approved by the competent authorities
- Temporary occupation of the public road domain (rural project)
- Building permit
- Land title, lease contract, or any document proving the right to use the land
- Certificate of release (mainlevée) of the registrations listed in the property certificate
- Lambert coordinates of the land plot
- Commercial contract between the liquid petroleum product distribution company and the project manager
- Contract termination, if applicable
⚖️ Legal references
Dahir bearing law No. 1.72.255 of 18 Muharram 1393 (22 February 1973) on the import, export, refining, packaging, storage and distribution of hydrocarbons, as amended and supplemented; Decree No. 2.72.513 of 3 Rabiul Awwal 1393 (7 April 1973), as amended and supplemented; Circular of the Minister of Energy, Mines, Water and Environment of 21 May 2014.
Other procedures : Energy, minerals and environment
- Authorization to collect and transport hazardous waste
- Obtaining a Mining Exploration Authorization
- Authorization to transfer all or part of the shares in a hydrocarbon exploitation concession
- Obtaining a Hydrocarbon Reconnaissance Authorization
- Authorization to commission a factory producing civil explosives and blasting accessories
- Certificate of operation of a premises, depot or factory for the explosives control card
- Subscribing to a medium-voltage electricity contract
- Amendment of a High-Voltage Electricity Supply Contract
Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.