Procedure for a user to be supplied with electricity through the medium-voltage network of the National Office of Electricity and Drinking Water (ONEE). It is done by submitting a subscription application to the Provincial Distribution Directorate or to a service agency.
🏛️ Administration
National Office of Electricity and Drinking Water (ONEE)Office National de l'Électricité et de l'Eau PotableElectricity Branch
💰 CostThe advance payment on consumption is calculated based on the subscribed power, the hours of use and the tariff applied.
⏱️ Processing time7 days
📎 Required documents
- Subscription application
- Copy of the National ID card (CNIE)
- Copy of the residence permit or passport
- Document proving the right to use the premises to be supplied (lease contract, owner's authorization, purchase deed, property certificate, national ID card (CIN) showing the address of the premises, water bill in the user's name with the address of the premises, or any equivalent official document)
- Authorization from co-owners in case of co-ownership (legalized signatures)
- Copy of the manager's national ID card (CIN)
- Copy of the commercial register extract (Model J)
- Certificate of the company's common identifier (Identifiant Commun de l'Entreprise, ICE)
- Power of attorney for the representative (legalized signatures)
- Agreement signed by all customers concerned in case of a shared transformer (legalized signatures)
- Certificate from the supervising ministry for subscriptions under the green tariff, stating the address of the delivery site
- Certificate from the supervising ministry if a backup generator is used
- Safety certificate for cinemas
- Operating authorization for activities that are dangerous to the public (mines, explosive materials, etc.)
- Authorization from the delegate for government administrations
- Undertaking in case of connection from a transformer owned by another customer (legalized signatures)
- Inheritance deed, with power of attorney from the other heirs (legalized signatures), or an undertaking by the user authorizing the Office to terminate the contract if an heir objects
- Judgment issued by the competent court
- Minutes of the general assembly
- Articles of association
⚖️ Legal references
Specifications (Cahier des charges) of the National Office of Electricity and Drinking Water - Electricity Sector; Internal procedures
Other procedures : Energy, minerals and environment
- Obtain an estimate for medium-voltage electricity grid connection works
- Obtaining the cancellation of a hydrocarbon exploration permit
- Obtaining the operating decision for a propane distribution installation via pipelines
- Authorization to Set Up a Storage Depot for Liquefied Petroleum Gas Cylinders
- Authorization to carry out a geological field mission
- Authorization to collect and transport hazardous waste
- Obtaining a Mining Exploration Authorization
- Authorization to transfer all or part of the shares in a hydrocarbon exploitation concession