Procedure to obtain authorization to create a housing development (groupe d'habitations) when it is part of an investment project. The application is submitted to the Provincial Investment Center (Centre provincial d'investissement), and the authorization is issued by the local authority (collectivité territoriale) where the project is located.

🏛️ Administration
Ministry of the InteriorMinistère de l'IntérieurRegional Investment CentersCentres Régionaux d'Investissement
💰 CostHousing development creation tax: between 3% and 5% of the total cost of the subdivision's infrastructure works. Fee for the urban agency's services (agence urbaine) for reviewing the application and issuing the binding opinion: set by the agency after approval by its board of directors, calculated in DH/m² excluding tax of built area.
⏱️ Processing time30 days

📎 Required documents

  • Application signed by the user, the engineer who designed the project, or an authorized person
  • Certificate from the National Agency for Land Registry, Cadastre and Mapping (Agence nationale de la conservation foncière, du cadastre et de la cartographie) stating that the land is registered or in the process of registration, with no opposition
  • Plan from the National Agency for Land Registry showing the boundaries of the land
  • Topographic plan at a scale of 1/500, or 1/1000 if the area exceeds 25 hectares
  • Architectural design documents for the housing development (plan at a scale of 1/500 or 1/1000 on a topographic base)
  • Technical documents on roads and on the water, sanitation and electricity networks
  • Specifications document (cahier des charges)
  • Construction plan of all levels, basements, terraces and roofs, at a scale of at least 1/100
  • Plan of the previously authorized housing development (in case of modification or renewal)
  • Copy of the contracts signed with all engineers working on the project
  • Technical note on compliance with fire and panic risk prevention rules
  • Architect's technical note on the building's energy efficiency
  • Additional documents
  • Document specifying the architectural requirements for squares and roads subject to an architectural harmony easement
  • Plans of structures at a scale of at least 1/50, where applicable
  • Infrastructure design plan at a scale of 1/500 or 1/1000 on a topographic base
  • Longitudinal profiles of roadways, water drainage structures and water pipes
  • Typical cross-sections of roads and of protruding parts in case of significant embankment or excavation
  • Technical plans by specialized engineers on the structure and stability of the buildings
  • Copy of payment receipts for paid services
  • Site logbook (cahier de chantier) in line with the template of the competent administration
  • Identification form signed by the applicant

✅ Conditions and how to apply

  • The land to be subdivided must be registered or in the process of registration, with the opposition period expired and no opposition filed

🧭 Steps

  1. Prepare the file with the required documents.
  2. Submit the file to the Provincial Investment Center (Centre provincial d'investissement).
  3. Wait for the file to be reviewed and for the opinion of the urban agency (agence urbaine).
  4. Collect the authorization issued by the local authority (collectivité territoriale) where the project is located.

⚖️ Legal references

Law No. 47.18 (Dahir No. 1.19.18 of 13 February 2019); Dahir No. 1.15.85 of 7 July 2015 (Organic Law No. 113.14); Law No. 47.06; Law No. 12.90 (Dahir No. 1.95.1 of 26 January 1995); Law No. 25.90; Decree No. 2.18.577 of 12 June 2019; Decree No. 2-92-832 of 14 October 1993; Joint Order No. 20-337

Other procedures : Construction, housing and real estate

All procedures: Construction, housing and real estate →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.