Waiver on the weld coefficient and exemption from the hydraulic test when importing steam equipment

Machine-translated — the French version prevails.

This procedure allows you to obtain a waiver for a weld coefficient above 0.7 and/or an exemption from the hydraulic test when importing steam equipment. The request is addressed to the Director of Control and Risk Prevention (Directeur du contrôle et de la prévention des risques).

🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableDepartment of Energy and MinesDépartement de l'Énergie et des MinesDirectorate of Control and Risk PreventionDirection du contrôle et de la prévention des risques
💰 CostFree
⏱️ Processing time30 days

📎 Required documents

  • Signed and stamped request addressed to the Director of Control and Risk Prevention
  • Copy of the company's articles of association and of the trade register (registre de commerce)
  • Copy of the powers granted to the person signing the request
  • Equipment identification sheet certified by the manufacturer
  • General drawing of the equipment and its welded parts
  • Detailed calculation note for the equipment
  • Certificate of conformity certified by the manufacturer
  • Approval reports for the welding procedures
  • Qualification reports for the welding technicians
  • Weld inspection report
  • Product inspection certificate issued by the manufacturer
  • Certificates of the hydraulic test and of the internal and external examinations carried out in the country of origin
  • Hydraulic test exemption: manufacturer's statement justifying the reason for the exemption
  • Hydraulic test exemption: examination report and statement from an approved inspection body justifying the reason for the exemption
  • Weld coefficient waiver: examination report and import hydraulic test certificate issued by an approved inspection body

⚖️ Legal references

Dahir of 22 July 1953 establishing regulations for the use of land-based steam equipment, as amended and supplemented; Decisions of the Director of Industrial Production and Mines of 19/08/1953 (manufacture, maintenance and installation; implementation procedures) and of 17/12/1953 (autogenous welding); Circular No. 2456 of 2 December 2005; Circular No. 6359 of 10/10/2018

Other procedures : Industry, trade and communications

All procedures: Industry, trade and communications →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.