Renewal of the definitive authorization to operate a renewable electricity production facility

Machine-translated — the French version prevails.

This procedure allows the operator of a facility that produces electricity from renewable energy to apply for renewal of its definitive operating authorization. The application is submitted to the Directorate of Renewable Energies and Energy Efficiency (Direction des énergies renouvelables et de l'efficacité énergétique).

🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableDepartment of Energy Transition (Département de la Transition Energétique)Directorate of Renewable Energies and Energy Efficiency / Direction des énergies renouvelables et de l'efficacité énergétique
💰 CostFree
⏱️ Processing time30 days

📎 Required documents

  • Description of the legal structure of the entity that owns the project and operates the facility
  • Description of the operator's technical capacities
  • Description of the operator's experience and summary of its previous projects, if any (name, address, installed capacity, technology)
  • List of the main roles and duties of the staff, with documents proving their skills
  • List of supplied customers (renewable energy source, location, consumption levels), consistent with the list in the provisional authorization
  • Site plan and detailed plan of the facility (access roads, power lines, delivery and connection substations, civil works, trenches, electrical works)
  • Technical characteristics of the equipment and machines used to produce electricity (with the renewable energy source)
  • Technical characteristics of the machines with which the facilities must be equipped
  • Detailed description of how the facility operates
  • How the technical specifications and standards of the national electricity grid operator will be applied
  • Preventive and corrective maintenance arrangements (light and heavy intervention)
  • Description of the means and procedures for optimal operation of the facility
  • Measures to protect the facility if technical activities are stopped
  • Measures in case of prolonged shutdown of technical activities
  • Any technical constraints (water pollution protection zone, spills or leaks of polluting substances)
  • Measures and means for connection to the national electricity grid (structures, technical conditions, design and consistency)
  • Urban planning measures to be followed under the urban development permits granted
  • Safety measures adopted
  • Connection plans to the national electricity grid, collection substation and evacuation substation
  • Connection plans to the water network, if any
  • Connection plans to the sewerage network, if any
  • Connection plans to the telecommunications network
  • Environmental and health impact study with the environmental acceptability decision
  • Copies of insurance policies (general liability and professional liability)
  • Social security (CNSS) affiliation number and payroll declaration
  • Amount of the investment made
  • Complete annual accounts for the last accounting year
  • Financial structure of the project (equity, debt, subsidies, financial incentives)

⚖️ Legal references

Dahir No. 1-10-16 of 11 February 2010 (Law No. 13-09 on renewable energies); Dahir No. 1-16-3 of 12 January 2016 (Law No. 58-15); Dahir No. 1-16-60 of 24 May 2016 (Law No. 48-15 on the regulation of the electricity sector); Decree on access to the national medium-voltage electricity grid; Decree No. 2-10-578 of 11 April 2011; Order No. 2657-11 of 19 September 2011; Order No. 313-14 of 4 February 2014

Other procedures : Energy, minerals and environment

All procedures: Energy, minerals and environment →

Official source : Idarati.ma — checked on November 5, 2026
For information only. Check with the administration concerned before proceeding.