Obtaining the Environmental Acceptability Decision

Machine-translated — the French version prevails.

A decision issued to projects that require an environmental impact study, after their effects on the environment and the measures to limit them have been assessed. The application is submitted to the Department of the Environment (Département de l'Environnement) or to the Regional Investment Center (centre régional d'investissement).

🏛️ Administration
Ministry of Energy Transition and Sustainable DevelopmentMinistère de la Transition Energétique et du Développement DurableDepartment of Sustainable DevelopmentDépartement du Développement Durable
💰 CostNo fee for putting together the environmental impact study file. The study documents and the costs of the public inquiry (publication of the public inquiry decree, technical documents and registers) are paid by the project owner.
⏱️ Processing time5 days after receipt of the final environmental impact study and the final environmental impact statement (average time: 60 days)

📎 Required documents

  • Environmental impact study prepared by the consulting firm, and approved Environmental Safety Monitoring Plan (PSSE)
  • Request to open the public inquiry
  • Map showing the project's foreseeable impact zone
  • Clear, easy-to-understand summary for the public, setting out the key information from the impact study
  • Information sheet describing the main technical characteristics of the project submitted to the public inquiry
  • Copies of the newspapers that published the public inquiry notice

✅ Conditions and how to apply

  • The project must be subject to an environmental impact study

⚖️ Legal references

Law No. 12-03 on environmental impact studies; Law No. 49-17 on environmental assessment; Law No. 47-18 on the reform of the Regional Investment Centers and the creation of unified Regional Investment Committees; Decree No. 2-04-563 on the powers and operation of the national and regional committees for environmental impact studies; Decree No. 2-04-564 setting out the organization of the public inquiry on projects subject to an environmental impact study

Other procedures : Investment

All procedures: Investment →

Official source : Idarati.ma — checked on November 5, 2026